KSC Crane Operators Lift Core Stage Pathfinder Six Times During October 2019

NASA's Space Launch System core stage pathfinder is suspended over the transfer aisle in preparation for lifting operations.  Photo credit: Scott Schilke / We Report Space
NASA's Space Launch System core stage pathfinder is suspended over the transfer aisle in preparation for lifting operations. Photo credit: Scott Schilke / We Report Space

KENNEDY SPACE CENTER: The Cranes, Doors & Platforms Group at Kennedy Space Center have had a chance to handle new flight hardware at the Vehicle Assembly Building during the month of October. A mock-up of the Space Launch System (SLS) Core Stage arrived at KSC via the Pegasus barge for a month of practice. The mock-up weighs in at 225,000 pounds, about 3,000 pounds more than the current design of the SLS Core Stage. It is 212 feet tall. The mock-up is known as the Core Stage Pathfinder.

NASA SLS Pathfinder High Bay #3. Photo Credit: Scott Schilke / We Report Space

It has been eight years since the crane operators at Kennedy Space Center have processed flight hardware in the Vehicle Assembly Building (VAB). A mock-up of the SLS Core Stage is spending the month of October at Kennedy Space Center to allow everyone on the cranes team some practice time lifting and rotating the rocket mock-up to vertical.

KSC's crane operators go through a year of in-house training to achieve a 094-1 Overhead Crane Operator Certification. Each operator is trained on crane cab controls, ground controller and e-stop operator. The cab controls are used to move the crane and the rocket forward, backward and sideways, in as little as 1/64th of an inch. Some of the senior crane operators have been with the team since the 1980's. But others are new and are still working on their certification.

Floor to ceiling in the Vehicle Assembly Building. Photo Credit: Bill Jelen / We Report Space

Jim Bolton, Exploration Ground Systems Core Stage Element Operations Manager explains that each crane has a crew of five people, including people in the crane cab, a ground controller who is in contact with the cab, and an e-stop operator who can cut power in case of an emergency. For this month's maneuvers, two cranes are in use: a 175-ton bridge crane holds the aft section of the rocket and a newer 325-ton crane attached to the top of the Pathfinder. "To move the rocket from horizontal to vertical, you have two crane crews - so we have 10 people tied up - out of the total of 21. After lifting the Core Stage Pathfinder today, the test article will remain hanging from the 325-ton crane. That means another crew of five will be here overnight to monitor the crane."

SLS core stage pathfinder viewed from the 16th Level catwalk during lift. Photo Credit: Bill Jelen / We Report Space

While the crew of 21 usually covers three shifts, everyone is working a single 12-hour shift during October so everyone stays on the same page during these practice lifts. Below, Jim Bolton, Exploration Ground Systems Core Stage Element Operations Manager explains the decision to go to a single shift during October:

You might wonder what the team has been doing since the last Space Shuttle was processed in 2011. The Cranes, Doors, & Platforms group is a part of the Jacobs Company's Test & Operations Service Contract (TOSC). There are 21 personnel who manage all of the overhead cranes at Kennedy Space Center. This includes 25 cranes inside the VAB, plus overhead cranes at the Space Station Processing Facility (SSPF) and Launch Equipment Test Facility (LETF). The team is responsible for operations and maintenance of all overhead cranes throughout KSC, plus large overhead doors and moving platforms such as those in the VAB.

VAB Pathfinder from High Bay 3. Photo Credit: Scott Schilke / We Report Space

During the hiatus between the last Space Shuttle launch and today, one of the original 175-ton cranes in the VAB, dating all the way back to Apollo 11, went a major overhaul and modernization. This crane is being used this week as the aft lifting crane for the Pathfinder. The foreward crane is a 325-ton crane installed in the 1990's for use with the Space Shuttle. 

Here, Bolton discusses the upgrades:

On October 15, 2019, the crews successfully lifted the pathfinder from horizontal to vertical, turned it, then lifted it above the 16th level catwalk and in to Highbay 3, and then lowered the pathfinder through the new platforms. 

Bolton says there "is about 16 feet of vertical clearance while moving to Highbay 3. We did one vertical and fit into Highbay 3. That's all the practice we need for Highbay 3.

"As far as the horizontal to vertical breakovers, there will be a total of six, maybe seven. The crane crew wanted to do enough of these maneuvers to rotate their crews through each position, so everybody gets a chance to handle the Pathfinder."

Bolton discusses operations during October:

Lifting the Pathfinder is a complicated ballet. Both the fore and aft cranes lift the rocket so it has ground clearance for the maneuver. The 325-ton fore crane stays near Highbay 3 and lifts the top of the Core Stage Pathfinder. The 175-ton aft crane is moving towards the fore crane during the maneuver. When the rocket is nearly vertical, there is a pinch point where the aft crane can not get any closer to the Pathfinder. The aft crane slowly slackens the connection to the bottom of the rocket to allow the rocket to move the last five degrees to vertical.

This timelapse video shows the breakover from horizontal to vertical on October 18, combined with a NASA timr-lapse of the lift and movement to Highbay 3 from October 15.

With the above operation finishing close to 6PM, the team planned to leave the Pathfinder hanging from the 325-ton crane overnight. This requires a crew of five to stay at the VAB overnight, as long as the crane is powered and holding flight hardware. 

Inside the cavernous NASA Pegasus barge, used to transport SLS hardware to Kennedy Space Center. Photo Credit: Scott Schilke / We Report Space

After spending the month at KSC, the Core Stage Pathfinder will move back to the Pegasus Barge and sail to Michoud Assembly Facility in New Orleans for additional practice operations. Eventually, the Core Stage Pathfinder will be sold for scrap.

Photos


NASA VAB Pathfinder & Pegasus Tour October 17th 2019 Cape Canaveral Photos Scott Schilke


Pathfinder Goes Vertical in VAB (Bill Jelen)

October 18, 2019

On October 17, 2019, the Pathfinder test article was lifted to vertical in the VAB.


We Report Space Book
The Book

Stunning, full color photo book covering every east coast launch spanning 2014-2015, including the first-ever powered landing of a SpaceX Falcon 9 rocket.

More Info